Project Details:
• Water main replacement
• 1200m of new 200mm Ductile Iron water main
• Replacing old 1888 Cast Iron water main which has burst 12 times in the last 10 years

Programme:
• Mid July 2013 – March 2014 (approx. 35 weeks)
• Commence work at jcn of Parkwood Road
• Mainlaying: 12 weeks
• Testing: 6 weeks (no site presence or traffic lights)
• Service Transfers: 15 weeks
• Connections: 2 weeks

Traffic Lights:
• 2-way lights (in 100m sections) on A25 Bletchingley Road, High Street, Nutfield
• 3-way lights at the following junctions:
– Mid Street
– Crossroads (church hill, coopers hill road)
• Manned during peak hours
• “Join flow of traffic” signs at quieter junctions (e.g Hunters Gate and Shortacres)

Proposed Road Closure:
• Church Hill – approx. 6 weeks into project (for 3 weeks)
• To allow for the use of 3-way lights at the crossroads with Coopers Hill Road
• Cormongers Lane will be used as the diversion route
• Advanced warning signs prior to closure

Spoil Storage:
• Investigate the use of the following locations for spoil storage:
– Nutfield Parish Council car park for playing fields
– Bus stop o/s Halfway House

Other:
• Extended working hours (7:30am – 6:00pm)
• Communication with local business prior to works commencement
• Advanced warning signs